Module 5 · Chapter 1 of 5 6 min read

L1, evaluation and negotiation

Being ranked L1 is not an award. The arithmetic check, the reasonableness test against the estimate, negotiation (only with L1, only downwards), the scrutiny committee for larger works, single-bid situations, and how long the wait usually is.

Financial opening: five prices sort themselves so the lowest, L1, sits on topFinancial opening · prices against the estimateBidder C−12.4%Bidder A−18.2%Bidder E+2.0%Bidder B−15.0%Bidder D−9.1%L1Only L1 may be negotiated with, and only downwards.
Sorted lowest first. L1 is now the only bidder the department may talk to about price.
In this module
  1. 1. L1, evaluation and negotiation
  2. 2. LOA, agreement and the security deposit
  3. 3. Running bills, the measurement book and deductions
  4. 4. Extension of time, deviations and liquidated damages
  5. 5. Completion, the final bill and the defect liability period

The portal publishes the financial opening and your name is at the top. Congratulations, and slow down: L1L1 (lowest bidder)The bidder with the lowest evaluated price among those who qualified technically. L2 is the next, and so on. Under the KTPP Act the department may negotiate only with L1.Read in the glossary → is a ranking, not a contract. Between this moment and the Letter of AcceptanceLOA (Letter of Acceptance)The letter telling you your bid has been accepted. From here you have a fixed number of days to pay the security deposit and sign the agreement.Read in the glossary → the department does four things, and any of them can take weeks.

1. The arithmetic check

The evaluator recomputes your bid. In an item-rate tender, unit rate times quantity for every line, then the total; if the total you wrote disagrees, the unit rates prevail and the total is corrected. In a percentage-rate tender there is little to check. You are asked to accept the corrected figure; refusing forfeits the EMD (Module 4). Check your own arithmetic before you submit and this stage is a formality.

2. Reasonableness

The evaluator compares L1 with the estimate. Below or at the estimate: acceptable as a rule, with attention to bids far below it (unbalanced rates, additional security). Above the estimate: the department has three options, in order: negotiate with L1, accept the premium with the sanction of a higher authority if the excess is within the limits delegated to it, or reject all bids and retender. Modest premiums on works where the SR has fallen behind material prices are often accepted; large premiums usually mean a retender.

3. Negotiation

Section 13 of the KTPP Act allows negotiation only with the lowest tenderer, and in practice only to bring the price down. You receive a letter or a portal notice inviting you to a negotiation on a date; you attend (or reply in writing) and either agree to a reduced rate, hold your price, or offer something in between. Three things to remember:

  • You may say no. Holding your price is not a withdrawal; the EMD is safe. The department then accepts, or rejects all bids.
  • Your costing is your defence. A contractor who can show the bitumen quotation behind the premium negotiates from strength.
  • Nobody else is in the room. L2 cannot be invited to undercut you. The pressure is only the threat of a retender, which costs the department months.

4. Scrutiny and sanction

Works above ₹5 crore in PWD and the irrigation departments, and ₹1 crore elsewhere, go to a Tender Scrutiny CommitteeTender Scrutiny CommitteeA committee that reviews larger tenders before award: above ₹5 crore in PWD and irrigation departments, above ₹1 crore elsewhere. Adds weeks between closing and award.Read in the glossary → that reviews the process and the price before acceptance. Every work also needs the acceptance of an authority with the financial power for that value: the Executive Engineer for small works, the Superintending or Chief Engineer, the government for the largest. Each signature is time.

Single bids and too few bids

If yours was the only bid, the department will usually retender rather than accept a single tenderSingle tenderOnly one bid was received. Departments usually retender rather than award on a single bid, unless the rules allow it and the price is reasonable.Read in the glossary →, unless it is a second call or the rules allow acceptance and the price is reasonable. The same often happens with two bids. It is disappointing to be L1 of one; it is also information: the next call is likely to close with you and one other, and you can price accordingly.

What to do while you wait

  • Line up the security deposit and, if the tender asks, the bank guarantee; the LOA gives you only days.
  • Confirm the site engineer and the equipment you listed are available on the start date.
  • Read the conditions of contract properly now: measurement, billing, escalation, LD, DLP. Module 5 walks through them.
  • Keep bidding elsewhere; an L1 that becomes a retender should not have cost you a month of other tenders.

Key takeaways

  • L1 is a ranking. Arithmetic check, reasonableness, negotiation and sanction stand between it and the LOA.
  • Negotiation is only with L1 and only downwards; holding your price is allowed and does not forfeit the EMD.
  • Works above ₹5 crore (PWD, irrigation) or ₹1 crore (others) pass a scrutiny committee.
  • A single bid usually means a retender. Use the wait to prepare the deposit, the engineer and the conditions.

Check yourself

0 / 3
  1. 1.L1 quoted 6% above the estimate. What may the department do first?
  2. 2.During negotiation you refuse to reduce your price. What happens to your EMD?
  3. 3.In an item-rate tender the unit rates and your written total disagree. Which prevails?

Frequently asked

Does being L1 guarantee the contract?
No. The department checks arithmetic and reasonableness, may negotiate, may need a scrutiny committee and a sanctioning authority, and may reject all bids. L1 is the only bidder in line, but not yet a contractor.
Can the department negotiate with L2?
Not under the KTPP Act. Section 13 permits negotiation only with the lowest tenderer. If L1 refuses and the price is unacceptable, the department retenders.
What is a single tender?
A tender that received only one bid. Departments usually retender rather than accept one bid, unless it is a repeat call or the rules allow acceptance at a reasonable price.
0 of 5 chapters done in this module
Know someone starting out? Send them this chapter.
WhatsApp
Put it to work

Every live Karnataka tender, with the history the portal never shows.

Who won the last ones like it, at what discount, and the documents it asks for. Browse without an account; sign up when you want alerts.

Written from the KTPP Act and Rules, the Karnataka Public Works Departmental Code 2014, KPWD bidding documents and office checklists, and checked against awarded tenders on this site. Figures change; the tender document and the registering office are the final word. Spotted an error? Tell us.

Independent site, not a government one. Tender data is published by the Karnataka Public Procurement Portal. Source: kppp.karnataka.gov.in