Module 5 · Chapter 5 of 5 5 min read

Completion, the final bill and the defect liability period

The completion certificate, final measurement and the final bill, the no-claim certificate and what it waives, the defect liability period and what you owe during it, release of the security deposit, and the work done certificate that makes the next tender easier.

The Letter of Acceptance, sealed, with a little confettiLetter of AcceptanceOffice of the Executive Engineer, PWD DivisionDeposit and signature within the days stated. Then the work order.
Completion, final bill, the quiet year of defect liability, then the deposit comes home and the certificate goes in the file.
In this module
  1. 1. L1, evaluation and negotiation
  2. 2. LOA, agreement and the security deposit
  3. 3. Running bills, the measurement book and deductions
  4. 4. Extension of time, deviations and liquidated damages
  5. 5. Completion, the final bill and the defect liability period

The last coat of paint is not the end of the contract. Three things follow it: the final bill, the defect liability period, and the release of everything the department has been holding. Each has paperwork, and the last one is the certificate you need for the next tender.

Completion

Write to the engineer stating the work is complete and asking for final measurement and a completion certificate. The engineer inspects, lists any incomplete or defective items, you attend to them, and the certificate issues with the completion date. That date ends the LD exposure and starts the DLP; get it right, and get it in writing.

The final bill

Prepared after final measurement: the whole work at your rates, including sanctioned deviations and extra items, less every payment made, less the deductions that apply. Check three things against your own record: every quantity in the final MB, every extra item's sanctioned rate, and the arithmetic of the deductions. The final bill is usually accompanied by a no-claim certificate: a declaration that you have no further claims under the contract. Sign it only when the bill includes everything you are owed; a claim not made before it is waived.

The defect liability period

For {{defect-liability-period|so many months after completion}} (12 is common for buildings, 24 or more for roads and some departments ask 60) you are responsible for making good any defect at your own cost, on notice from the engineer. Fail to attend and the department repairs it and recovers the cost from your security deposit. It is a period of low activity and real exposure: visit the work after the first monsoon, fix small things before they are noticed, and answer every notice.

Release of the security deposit

After the DLP ends, apply in writing for release of the security depositSecurity deposit (SD)Money held by the department for the whole contract as a guarantee of performance, commonly 5% of the contract value in Karnataka works. Part is paid at agreement, the rest deducted from bills.Read in the glossary → (cash, or return of the bank guarantee for cancellation). The engineer certifies that no defects are outstanding, and the division refunds or returns the instrument. It does not happen without the letter, and the letter is often forgotten; a division may hold deposits for years that nobody asked for. Put the DLP end date in your calendar on the day the completion certificate arrives.

The file at the end

Agreement, work order, hindrance letters, extension order, MB extracts, every RA bill statement, the final bill, the completion certificate, the deposit release, and the work done certificate. For a Class III contractor with six works, that is six files, and they are the whole case for Class II. Signed-in users keep them on BiddingView under Contracts, with bills and documents filed against each work and the certificate ready for the next bid.

Key takeaways

  • Ask in writing for final measurement and the completion certificate; the date ends LD and starts DLP.
  • Check the final bill's quantities, extra-item rates and deductions before signing the no-claim certificate.
  • During the DLP, fix defects on notice or the cost comes out of your deposit.
  • After the DLP, apply for release of the deposit, and get the work done certificate while the file is warm.

Check yourself

0 / 3
  1. 1.What does signing a no-claim certificate mean?
  2. 2.During the defect liability period, who pays to fix a defect?
  3. 3.When can you apply for release of the security deposit?

Frequently asked

What is the defect liability period in PWD contracts?
The months after completion during which the contractor must repair defects at their own cost: commonly 12 months for buildings and 24 or more for roads, with some departments specifying longer. The security deposit is released after it ends.
How do I get my security deposit back?
After the defect liability period, apply in writing to the division. The engineer certifies no outstanding defects and the division refunds the cash or returns the bank guarantee for cancellation.
How do I get a work done certificate?
Ask the Executive Engineer of the paying division in writing after the final bill, specifying the format: name of work, agreement number, contract value, value of work done, dates, and satisfactory completion.
0 of 5 chapters done in this module
Know someone starting out? Send them this chapter.
WhatsApp
Put it to work

Every live Karnataka tender, with the history the portal never shows.

Who won the last ones like it, at what discount, and the documents it asks for. Browse without an account; sign up when you want alerts.

Written from the KTPP Act and Rules, the Karnataka Public Works Departmental Code 2014, KPWD bidding documents and office checklists, and checked against awarded tenders on this site. Figures change; the tender document and the registering office are the final word. Spotted an error? Tell us.

Independent site, not a government one. Tender data is published by the Karnataka Public Procurement Portal. Source: kppp.karnataka.gov.in