From ₹50 lakh upward, every works tender in Karnataka uses two covers (Rule 28 of the KTPP Rules, and the K/W-3 and K/W-4 documents). Cover 1 proves you may do the work. Cover 2 says what you will charge. They are opened at different times, by rule, and the whole point is that nobody sees a price until they have decided, on paper, who is qualified.
Cover 1: the technical bid
Everything the qualification section asks for, and nothing about price. A typical list for a K/W-3 road work:
- Registration: the PWD registration book, valid on the closing date, in the class the notice names.
- Identity and tax: PAN, GST certificate, latest IT returns, sometimes EPF and ESI numbers.
- Experience: completion certificates for similar works, from the client's engineer, showing the completed value.
- Turnover: the CA's certificate with audited statements or returns, for the years the document names.
- Tender capacity: the calculation on the tender's own format, with the list of works in hand countersigned by an Executive Engineer.
- Quantities, equipment and personnel: the year's quantities from certified works; ownership or lease proofs; engineers' CVs and degree certificates.
- EMD and tender fee: payment receipts from the portal; an EMD instrument valid 45 days beyond the bid validity.
- Declarations: the not-blacklisted affidavit, acceptance of tender conditions, and in a reserved tender the category certificate.
- Corrigenda acknowledged: every corrigendum signed and uploaded, when the document asks.
- The tender document itself, every page digitally signed, when the department wants it.
Cover 2: the financial bid
Only the price. On KPPP this is usually an online form: for a percentage-rate tender, one figure (so much percent above, below or at par); for an item-rate tender, a rate against every BOQ line, with the total computed. Some tenders also ask for a signed price schedule PDF. Nothing else goes in.
How the opening goes
- Technical opening, at the time in the notice: Cover 1 of every bid is opened on the portal. The opening summary lists the bidders and what each submitted.
- Technical evaluation: an officer or committee checks each bid against the criteria and records responsive or non-responsive, with reasons. Bidders may be asked to clarify a document; they may not add a missing one after closing, though practice on minor omissions varies by department.
- Financial opening, notified to the responsive bidders: Cover 2 of those bids only is decrypted and opened. The portal publishes the prices and the ranking.
One cover below ₹50 lakh
K/W-1 (below ₹20 lakh) and K/W-2 (₹20 lakh to ₹50 lakh) use a single cover: documents and price together, opened at once on the day the tender closes. The same discipline applies: the evaluator still checks eligibility before looking at price, and a missing document still loses. K/W-1 is the lightest gate in the system, registration in the named class and tender capacity, which is why the first tenders a Class IV contractor wins are usually K/W-1 works.
Preparing Cover 1 as a habit
Nine of the ten documents above are the same for every tender you will bid this year. Keep them as clean, named PDFs (each page legible, under the portal's size limit, dated within the validity the tender asks). What changes per tender is the experience certificate you pick, the tender capacity sheet, the EMD receipt and the corrigenda. Signed-in users can keep the standing set in BiddingView's Documents library and see, on each tender page, which of the tender's asked-for documents they already hold.
Key takeaways
- Two covers from ₹50 lakh (K/W-3 and above); one cover below (K/W-1, K/W-2).
- Cover 1 is proof of eligibility; Cover 2 is the price. Cover 2 opens only for bidders whose Cover 1 passed.
- A price anywhere in Cover 1 can void the bid.
- Most of Cover 1 is standing documents; keep them ready and swap in the tender-specific four.
Check yourself
0 / 3- 1.Which document belongs in Cover 2?
- 2.A ₹35 lakh PWD work is issued on K/W-2. How many covers?
- 3.You upload a covering letter in Cover 1 that mentions your 5% discount. What is the likely result?
Frequently asked
What is the difference between technical bid and financial bid?
Can I add a missing document after the closing date?
Which Karnataka tenders use a single cover?
Every live Karnataka tender, with the history the portal never shows.
Who won the last ones like it, at what discount, and the documents it asks for. Browse without an account; sign up when you want alerts.
Written from the KTPP Act and Rules, the Karnataka Public Works Departmental Code 2014, KPWD bidding documents and office checklists, and checked against awarded tenders on this site. Figures change; the tender document and the registering office are the final word. Spotted an error? Tell us.