Module 4 · Chapter 1 of 7 9 min read

Eligibility: similar work, turnover and tender capacity

The qualification section of a Karnataka works tender, clause by clause, as the K/W standard documents set it: one similar work of 50% of the estimate (80% above ₹1 crore), the turnover test, the tender capacity formula with its factor of 1.5, 2.5 or 5, quantities, equipment and people, and how to read 'or' versus 'and'.

Tender capacity: A times N times the factor F, less B, compared with the estimateTender capacity = (A × N × F) − BA: best year's works · N: years to complete · F: 1.5, 2.5 or 5 · B: work in handA × N × F− B (work in hand)available tender capacityestimateQualifies ✓Longer completion periods raise capacity; every work you win lowers it.
Tender capacity = (A × N × F) − B. Your best year, stretched over the completion period and multiplied by the factor the document allows, minus what you already owe the world in work.
In this module
  1. 1. Eligibility: similar work, turnover and tender capacity
  2. 2. Reserved tenders: SC, ST and Category-I and II(A) contractors
  3. 3. The two-cover system
  4. 4. The BOQ and pricing your bid
  5. 5. EMD, tender validity and forfeiture
  6. 6. Submitting on KPPP: the final checklist
  7. 7. Why bids get rejected

The qualification section is the gate. It sits near the front of every tender document, usually headed "Qualification criteria" or "Instructions to Tenderers, clause 3", and it is the first thing to read after the notice. If you do not clear it, close the document; if you do, everything else is work you can control.

The standard documents set the bar

Karnataka does not let each engineer invent the criteria. Every works tender is issued on one of six standard tender documents, K/W-1 to K/W-6, prescribed by the Finance Department in 2005 and amended by government order since. The form the tender uses is printed on every page, and it tells you before you read a word of the criteria how hard the gate is.

The value bands are the documents' own. A department may pick a heavier form for a smaller work; it may not pick a lighter one.
DocumentWorksCoversWhat you must show
K/W-1K/W-1 to K/W-6 (standard tender documents)Karnataka's six standard tender documents for works, prescribed by the Finance Department in 2005: K/W-1 below ₹20 lakh, K/W-2 to ₹50 lakh, K/W-3 to ₹1 crore, K/W-4 to ₹10 crore, and K/W-5 and K/W-6 for prequalification above that. The form on the cover tells you the gate.Read in the glossary →Below ₹20 lakhOneRegistration in the class the notice names, and tender capacity. No turnover or similar-work test.
K/W-2₹20 lakh to ₹50 lakhOneTurnover, one similar work, tender capacity.
K/W-3₹50 lakh to ₹1 croreTwo (Rule 28)Turnover, one similar work, minimum quantities, tender capacity, equipment, people.
K/W-4₹1 crore to ₹10 croreTwoAs K/W-3 with higher bars, plus insurance and, for works over a year, price adjustment.
K/W-5, K/W-6Above ₹10 crorePrequalification firstA separate application before the tender; K/W-6 allows joint ventures.

1. Similar work

The test: as prime contractor, in the last five financial years, you have satisfactorily completed (at least 90% of its contract value) at least one work similar in nature and of a stated value. The value is the part that changes with the document:

  • Works up to ₹1 crore (K/W-2 and K/W-3): one similar work of at least 50% of the estimated cost, the figure the 2008 and 2014 orders fixed for this band.
  • Works above ₹1 crore (K/W-4): one similar work usually not less than 80% of the estimated value.
  • What counts as similar is defined in the document: "road works including asphalting" is not met by a building; "civil works" is broad. Read the definition, not the heading.
  • Whose name. Completed by you, as contractor of record, and certified by the client's engineer for the completed value. Sub-contract work counts only if the document says so.

2. Turnover

Turnover in civil engineering construction works only, certified by a CA. Up to ₹1 crore the test is an average annual turnover, in at least two of the last five financial years, usually not less than the estimated cost of the work. Above ₹1 crore it is a minimum turnover in at least two years of not less than twice the estimated annual payments under the contract (the estimate divided by the years to complete it). Your turnover certificate from Module 2 answers both directly.

3. Tender capacity

Every K/W document asks that your {{bid-capacity|assessed available tender capacity}} be more than the tender value. The formula, and the one number in it that changes with the tender:

Tender capacity calculator
(A × N × F) − B, as the K/W documents define it, with the factor the orders allow. The document tells you how A is updated for inflation; this uses it as entered.
Available tender capacity
₹70,00,000
₹60 L × 0.67 × 2.5 − ₹30 L
Against the estimate
Falls short
Short by ₹20 L. A longer completion period or fewer works in hand would close it.

Three lessons hide in the formula. A long completion period raises your capacity (N is bigger), which is why an 18-month work is easier to qualify for than the same value in 6 months. Every work you win reduces your capacity for the next one (B grows), which is the department's way of stopping a contractor from taking on more than it can build. And the factor is a gift to small contractors: at ×2.5 a ₹40 lakh year supports a ₹1 crore bid, which at ×1.5 it does not.

4. Quantities, equipment and people

From K/W-3 upward the document lists minimum quantities executed in any one year, usually 80% of the peak annual rate the work needs (so many cubic metres of concrete, of earthwork), equipment to be owned or leased (a paver, a roller, a hot-mix plant, a transit mixer) and personnel (a graduate engineer with so many years, a diploma holder). Ownership proofs or lease agreements and the engineers' CVs go in the technical cover. Building tenders add that you or a named sub-contractor hold the electrical and water-supply licences for those parts. The KPWD Code separately requires Class I and II contractors to engage a graduate engineer on works of ₹15 lakh and above.

5. Declarations, and no joint ventures

An affidavit that you are not blacklisted or debarred by any government body, have no litigation history the document asks about, and that the information is true. False declarations forfeit the EMD and can debar you. Joint ventures are not accepted in K/W-1 to K/W-4; only the prequalified large works on K/W-6 take them. A small contractor cannot borrow a bigger one's turnover by partnering on paper.

Reading 'and' versus 'or'

"One work of 50% or two of 30%" gives you two routes. "Turnover and similar work and tender capacity" gives you none; every test must pass. When a clause is ambiguous, ask at the pre-bid meeting, in writing; the answer binds the evaluator.

Key takeaways

  • The K/W form printed on the tender tells you the gate: K/W-1 is registration alone, K/W-3 and above add turnover, similar work, quantities and people.
  • Similar work: 50% of the estimate up to ₹1 crore, 80% above. Turnover: best two years' average at least the estimate up to ₹1 crore, twice the annual payments above.
  • Tender capacity = (A × N × F) − B, with F = 1.5, or 2.5 up to ₹1 crore, or 5 in reserved tenders. Longer completion periods raise it; works in hand lower it.
  • No joint ventures below prequalification. 'And' means every test; 'or' means a choice.

Check yourself

0 / 3
  1. 1.In the tender capacity formula, what is B?
  2. 2.A K/W-3 tender of ₹80 lakh needs one similar work. How large?
  3. 3.Which multiplying factor applies to a ₹60 lakh open tender?

Frequently asked

What is the tender capacity formula in Karnataka PWD tenders?
Assessed available tender capacity = (A × N × F) − B: A is the maximum annual value of works executed in the last five years, N the completion period in years, F the multiplying factor (1.5 in the standard document, 2.5 for works up to ₹1 crore, 5 in reserved-category tenders) and B the value of existing commitments over that period. Capacity must exceed the tender value.
Does sub-contract work count as similar work?
Only if the tender document says so. The K/W documents ask for work completed as prime contractor; the KPWD Code accepts sub-contract work for Class I registration under conditions, which is a different test.
What is 'satisfactorily completed'?
At least 90% of the contract value executed and the client's engineer certifying completion without termination or adverse remarks. A completion certificate from the Executive Engineer is the standard proof.
0 of 7 chapters done in this module
Know someone starting out? Send them this chapter.
WhatsApp
Put it to work

Every live Karnataka tender, with the history the portal never shows.

Who won the last ones like it, at what discount, and the documents it asks for. Browse without an account; sign up when you want alerts.

Written from the KTPP Act and Rules, the Karnataka Public Works Departmental Code 2014, KPWD bidding documents and office checklists, and checked against awarded tenders on this site. Figures change; the tender document and the registering office are the final word. Spotted an error? Tell us.

Independent site, not a government one. Tender data is published by the Karnataka Public Procurement Portal. Source: kppp.karnataka.gov.in